Deck material calculator

Tell us the deck you want. You get every board, fastener and footing it needs — and the reasoning behind each number, so you can check our working.

Plan view of a 20 by 16 foot deck16 joists spaced 16 inches on centre along the 20 foot length, spanning the 16 foot width. The house side is carried on a ledger; the outboard edge is carried on a beam. 4 posts on footings 12 inches across. Boards run the length of the deck, parallel to the house. Stairs drop 36 inches to grade in 5 risers.House / ledger20 ft16 ft
Ledger, rim and beam Joists at 16″ on centre Deck boards Railing Post on footing
16 joists spaced 16 inches on centre along the 20 foot length, spanning the 16 foot width. The house side is carried on a ledger; the outboard edge is carried on a beam. 4 posts on footings 12 inches across. Boards run the length of the deck, parallel to the house. Stairs drop 36 inches to grade in 5 risers.
320sq ft deck
20′ × 16′footprint
15line items
Read before you order
  • Your deck is 20 ft long but the boards are 16 ft, so every row needs a butt seam. Seams must land on a joist, and most builders double the joist under a seam line.
  • Ledger attachment and flashing is the most common point of deck failure. The fastener schedule and flashing detail must come from AWC DCA6 or your local building department, not from a calculator.
  • Span limits are not yet verified against AWC DCA6 and are withheld. Size your joists and beams with your local building department.
  • Footings must reach below your local frost line. 42 in is a placeholder, not a recommendation — frost depth ranges from zero in the far south to 100+ in in the far north.
  • Post spacing is assumed at 6 ft because the beam span table is not yet verified. Confirm beam size and post spacing before ordering.
  • The stair needs 45.0 in (3.8 ft) of clear run at the bottom. Check it fits before you build.

Decking

Item Qty Unit
5/4x6 decking, 16 ft lengths 34 rows across 16 ft of width. Each board covers 5.75 in (5.50 in face + 0.25 in gap), so 16 ft of width needs 34 rows. 34 rows x 20 ft = 680 linear ft, plus 10% cutting waste for a straight layout = 748 linear ft, bought as 16 ft boards. 47 each

Framing

Item Qty Unit
2x8 joists, 16 ft Joists run the 16 ft width, spaced 16 in on centre along the 20 ft length: floor(240 in / 16 in) + 1 = 16. The +1 is the joist that closes the far end. 16 each
2x8 rim joist, 20 ft One rim joist closes the outboard edge, running the full length of the deck. 1 each
2x8 ledger board, 20 ft The ledger carries the house-side end of every joist and runs the full length. 1 each
2x8 blocking, cut to fit between joists A 16 ft joist span gets 2 row(s) of blocking (one per 8 ft of span). Each row needs a piece in each of the 15 bays: 2 x 15 = 30. 30 each
Structural posts One post per footing: 4. 4 each

Hardware

Item Qty Unit
Joist hangers One hanger per joist where it meets the ledger: 16 joists = 16 hangers. 16 each

Foundation

Item Qty Unit
12 in diameter footings, 42 in deep One footing per post. Posts assumed at 6 ft on centre along the 20 ft beam: floor(20 / 6) + 1 = 4. 4 each
Concrete mix, 80 lb bags Each footing is a cylinder: pi x (0.50 ft radius)^2 x 3.50 ft deep = 2.75 cu ft. 4 footings = 11.00 cu ft total. One 80 lb bag yields 0.60 cu ft, so 11.00 / 0.60 = 19 bags. 19 bags

Fasteners

Item Qty Unit
Deck screws (face fastening) 2 screws at every board-to-joist crossing: 34 rows x 16 joists x 2 = 1088 screws, plus 5% spares = 1143. 1,143 each

Railing

Item Qty Unit
Guard posts Posts at no more than 6 ft apart on each open run (16 ft, 20 ft, 13 ft), plus one to close each run, less 2 shared corner posts = 11. 11 each
Top and bottom rails 49.0 ft of guard, with a top and a bottom rail: 49.0 x 2. 98 linear ft
2x2 balusters A 4 in sphere must not pass through the guard (IRC R312.1.3). With 1.50 in balusters and a 3.75 in design gap, they sit 5.25 in on centre: 588 in of guard / 5.25 = 112. 112 each

Stairs

Item Qty Unit
2x12 stringers Stringers no more than 16 in apart across a 36 in wide stair: ceil(36 / 16) + 1 = 4. 4 each
Tread stock (2 boards per tread) 4 treads x 2 boards x 3.0 ft wide = 24.0 linear ft. 24 linear ft
What this assumed
Each 5/4x6 board covers 5.75 in including a 0.25 in gap.
10% cutting waste (Straight (boards parallel to the house)).
Joists at 16 in on centre.
Blocking added once per 8 ft of joist span.
Posts assumed at 6 ft on centre.
80 lb concrete bag yields 0.60 cu ft.
Face screwed, 2 screws per crossing.
Guards assumed at least 36 in tall (IRC R312.1.2).
Balusters at 5.25 in on centre.
5 risers at 7.20 in and 4 treads at 11.25 in deep. Total run 45.0 in.
20 ft x 16 ft = 320 sq ft of deck.

How this calculator works

Actual dimensions, not nominal

A 2x8 is not eight inches wide. It is 7.25 in. A 5/4x6 deck board is 5.5 in wide, not six. Every quantity here is built from actual surfaced dimensions, because estimating on the label is the most common way a materials list comes out short.

The gap between boards is coverage too

Deck boards are installed with a gap for drainage and movement, typically 1/4 in. That gap is real coverage: a 5.5 in board with a 1/4 in gap covers 5.75 in of deck. Estimating on board width alone over-counts boards on every single deck.

Waste depends on the layout

A straight run wastes little, roughly 10%. A 45 degree layout wastes both ends of every board, closer to 15%. A picture-frame border adds mitred perimeter boards on top of that, around 18%. A single flat percentage cannot be right for all three.

Counts come from geometry

Joists are floor(span / spacing) + 1, because the last joist closes the far end. Fasteners come from the number of places a board actually crosses a joist — rows times joists — not from a screws-per-100-square-feet rule of thumb that ignores both board width and joist spacing.

What we will not guess

Joist and beam span limits are structural-safety data. Until our span tables are verified line by line against the published AWC DCA6 tables, this site withholds them and says so, rather than printing a number that looks authoritative. Footing depth must reach below your local frost line, which varies from nothing in the far south to over eight feet in the far north. Confirm both with your local building department — see our methodology.